    Planning an installation

    Installing an EV charger in an apartment or townhouse

    Owners corporation approval, which meter the charger runs from, the cable route through common property and the building's supply all need settling first.

    5 minute readUpdated 9 October 2026
    Photo for the article: Installing an EV charger in an apartment or townhouse

    Can I install an EV charger in my apartment or townhouse car space?

    • Check the plan of subdivision first. Whether your car space is part of your lot or common property decides who has to approve the work.
    • The charger has to run from a supply billed to you: your own switchboard, or a building supply with a meter for each charger.
    • Cable through a shared car park, wall or driveway needs owners corporation approval in writing before anything is booked.
    • Where many owners want chargers, one shared plan with load management beats separate cable runs from every unit.

    Start with who owns the car space

    In most apartment buildings and townhouse developments, each owner holds a lot and the owners corporation looks after common property. The plan of subdivision shows which is which. Some car spaces are part of a lot, some sit on common property with an exclusive use arrangement, and some are simply allocated.

    That decides the approval path. A townhouse garage on your own lot, wired from your own switchboard, can often be treated much like a house, because the work stays inside your lot. A space in a shared basement in Port Melbourne or Kensington usually has common property somewhere between your meter and your car.

    Which meter and supply the charger runs from

    The charger has to be fed from a supply you pay for. In a townhouse, that is usually your own switchboard, with a new circuit run to the garage. In an apartment block, your unit's board may be floors above the car park, and a cable from it can be long and cross areas you don't own.

    The alternatives are a sub-board near the car park that serves only your space, or a building-wide charging supply with each charger metered so the right owner is billed. Which suits depends on where the meters are, how much spare capacity the building's supply has and what the owners corporation is prepared to manage.

    Energy Safe Victoria says the property owner is responsible for the electrical installation from the point of supply. In a subdivided building, which length of cable belongs to which owner depends on the plan and the owners corporation, so confirm it before anyone works on mains or a shared meter panel.

    Getting cable through common property

    Even a short basement run can cross common property: along the car park ceiling, past storage cages, through a wall or up a riser. Each crossing needs approval. Where cable passes through a wall or slab that separates parts of the building, the hole has to be sealed properly afterwards, so ask the building manager who checks that.

    In a townhouse development, the question is usually the driveway. A garage backing onto your own meter box is often a short run. A carport across a shared driveway may need trenching through common property, which means approval, a plan for reinstating the surface and agreement on who looks after the cable.

    Load limits in a shared car park

    One charger on one unit's supply is a question about that unit's switchboard and mains. Ten chargers in a basement is a question about the whole building's supply. If every car plugs in after work at full rate, the building can run short just as residents are cooking and heating.

    Load management is the usual answer. A sensor measures what the building or unit is drawing, and the chargers share what is left, slowing when demand is high and picking up overnight. Most cars sit parked far longer than they need to charge, so a slower evening rarely matters.

    If the supply genuinely can't carry the chargers residents want, the connection may need upgrading. Consumer mains, the main switchboard and the meter box are prescribed work in Victoria, inspected by a Licensed Electrical Inspector before switch-on. Connection changes also go through the distributor, which in parts of Port Melbourne is CitiPower.

    Getting approval, and thinking about the next owner

    Write to the owners corporation manager or committee with what you want installed, the charger's make and model, a sketch of the cable route, how it will be metered and how it will look. Wait for approval in writing before booking work that touches common property. If you rent, you need the rental provider's consent as well.

    If several owners are asking, raise it at a general meeting. One building-wide plan with a shared supply, load management and fair billing avoids a basement full of separate cable runs, and leaves room for the next owner who buys an EV.

    Once approved, the work is a dedicated circuit with safety switch protection, cable fixed along the agreed route and the charger mounted where its lead reaches the charge port. It comes with a Certificate of Electrical Safety; give the manager a copy so future committees know what runs where.

    Questions that come next

    Usually not, if the garage is part of your lot and the cable runs from your own switchboard without crossing common property. If the route crosses a shared wall, driveway or meter room, ask first.

    Sources for this article

    5 sources, with the date each was checked
    1. 1.Energy Safe Victoria: The point of supply is the changeover point from the electricity distribution network to the electrical installation, where the property owner becomes responsible for the maintenance and repair of the electrical… Accessed 30 September 2026.
    2. 2.Energy Safe Victoria: 'Prescribed' certificates are for electrical installation work that requires inspection by a Licensed Electrical inspector. This includes (but is not limited to): Consumer mains cables, main switchboard, meter box and… Accessed 30 September 2026.
    3. 3.CitiPower, Distribution Annual Planning Report December 2024 (hosted by the Australian Energy Regulator): The zone substation in Fisherman’s Bend (E) is served by two sub-transmission lines from Fisherman Bend Terminal station (FBTS). The zone substation supplies areas of Fisherman’s Bend and Port Melbourne. Accessed 30 September 2026.
    4. 4.Energy Safe Victoria: Clause 2.6.3.2.2 requires all final sub-circuits in a domestic installation be protected by a residual current device (RCD). A hot water service is included in this requirement Accessed 30 September 2026.
    5. 5.Energy Safe Victoria: Whenever a licensed electrician completes any electrical installation work, they must provide a Certificate of Electrical Safety (COES). Accessed 30 September 2026.